Maverick Construction Inc. builder contractor to Grand Hotel Mackinac Island, Northern Michigan. West End phase 2

Phase 2 of the West End of Grand Hotel posed another set of issues. The Lanai Suites below had been recently remodeled.  The exterior wall was not substantial enough to support two more floors above, and as usual the weather is a big factor. The construction season is from November 1st - May 10th. The original design required the exterior wall be stripped from the outside, the hallway walls be stripped on the west side, and additional structure be installed in the existing wall cavity. Similarly, as with the Garden Suites Maverick met with the design professionals and brain-stormed about the inherent dangers that the project faced. As the conversation evolved we tried to look for the most redundant approach. One that eliminates as many of the variables as possible.

After much discussion we all decided that  by making the skeleton of steel we could eliminate a lot of carpentry, install the roof before demolition, and make the project more comprehensive to the owners needs.

Below please take a moment to look at the pictures.

Maverick Construction Inc.Builder, Contractor Grand Hotel, Mackinac Island, Northern Michigan

PREPARING THE STEEL WITH WOOD FILETS TO ATTACH JOIST HANGERS  (EASIER ON THE GROUND THAN IN THE AIR)

Maverick Construction Inc.Builder, Contractor Grand Hotel, Mackinac Island, Northern Michigan

ATTACHING THE STEEL TO THE EXISTING STRUCTURE

Maverick Construction Inc.Builder, Contractor Grand Hotel, Mackinac Island, Northern Michigan

WATCHING AS THE FIRST 58' COLUMN LOWERS INTO PLACE

Maverick Construction Inc.Builder, Contractor Grand Hotel, Mackinac Island, Northern Michigan

EASY DOES IT BOY'S (ON ALL OF THE INTERIOR COLUMN PLACEMENT THERE WAS A MAN AT EACH FLOOR WITH A RADIO COMMUNICATING WITH THE CRANE OPERATOR)

Maverick Construction Inc.Builder, Contractor Grand Hotel, Mackinac Island, Northern Michigan

NEXT THE MAIN ROOF SUPPORTS. THEY ARE 2 STORIES TALL WITH THE ROOF PITCH BUILT IN.

Maverick Construction Inc.Builder, Contractor Grand Hotel, Mackinac Island, Northern Michigan

AND THERE GOES ANOTHER ONE. NOTICE THE WOOD IS ALREADY ATTACHED.

Maverick Construction Inc.Builder, Contractor Grand Hotel, Mackinac Island, Northern Michigan

THE LAST PIECE OF STEEL SET. NEXT THE ROOF

Maverick Construction Inc.Builder, Contractor Grand Hotel, Mackinac Island, Northern Michigan

SOME CONTRACTORS LIKE TO START ON ONE END OR THE OTHER.  BY STARTING IN THE MIDDLE WE WERE ABLE TO SPLIT UP AND UTILIZE OUR RESOURCES

Maverick Construction Inc.Builder, Contractor Grand Hotel, Mackinac Island, Northern Michigan

WE ALSO WERE ABLE TO UTILIZE THE EXISTING STRUCTURE TO WORK FROM.

Maverick Construction Inc.Builder, Contractor Grand Hotel, Mackinac Island, Northern Michigan

NOW THE DEMOLITION STARTS.

Maverick Construction Inc.Builder, Contractor Grand Hotel, Mackinac Island, Northern Michigan

THE VERY NORTH END DURING FRAMING OF THE 300 LEVEL.

Maverick Construction Inc.Builder, Contractor Grand Hotel, Mackinac Island, Northern Michigan

ALMOST DRIED IN. THESE WALLS WERE ALSO PREFABRICATED ON SITE AND HOISTED INTO PLACE. ALLOWING A SEAMLESS TRANSITION IN CONSTRUCTION SEQUENCE. THE TIME FRAME IS WELL BEFORE CHRISTMAS.

Maverick Construction Inc.Builder, Contractor Grand Hotel, Mackinac Island, Northern Michigan

THE BACK SIDE WITH THE NEW 400 LEVEL IN THE BEGINNING OF THE SIDING PROCESS.

Maverick Construction Inc.Builder, Contractor Grand Hotel, Mackinac Island, Northern Michigan

EXTERIOR COMPLETE. NOTICE THE DETAIL IN THE EAVES AND HOW SEAMLESS THE JOB IS.  ANOTHER SUCCESS BY A TOP NOTCH TEAM OF DESIGN PROFESSIONALS AND MAVERICK.

Maverick Construction Inc.Builder, Contractor Grand Hotel, Mackinac Island, Northern Michigan

INTERIOR OF 1 OF THE 400 LEVEL LANAI SUITES. YOU CAN SEE THE DORMER EFFECT ON EACH SIDE.